Delayed Possession Can’t Hold Buyers Hostage: HRERA Orders Refund
The Haryana Real Estate Regulatory Authority, Gurugram, has once again reinforced that a homebuyer cannot be made to wait indefinitely when possession of a real estate project is delayed.

About the authors+
Reading context+
Jurisdictions
Topics
The Haryana Real Estate Regulatory Authority, Gurugram, has once again reinforced that a homebuyer cannot be made to wait indefinitely when possession of a real estate project is delayed.
In a significant relief to the allottees, HRERA directed Manglam Multiplex Private Limited to refund the amount paid by the buyers along with interest after finding that the delay in possession entitled them to withdraw from the project.
The matter was represented by Advocate-on-record Anshul Gupta on behalf of the homebuyers.
Quick Summary
The case arose after the buyers sought cancellation of their allotment and refund of the amount paid due to delay in possession. The promoter opposed the refund and alleged default on the part of the buyers, contending that forfeiture of amounts was justified.
HRERA, however, held that the material placed before it did not establish that the buyers were chronic defaulters. The Authority noted that the buyers had made payments before seeking cancellation and could not be compelled to continue with an allotment where possession had not been delivered within the stipulated timeline.
The order reaffirmed that delay in delivery of possession cannot indefinitely tie down an allottee, particularly where the statutory scheme under RERA provides an exit route in the form of refund.
Relying on the Supreme Court’s ruling in Newtech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh, HRERA reiterated that where possession is delayed, the allottee has a clear statutory right to seek refund under RERA.
Key Observations
1. Allottee cannot be forced to wait indefinitely
HRERA observed that delayed possession gives the buyer a valid ground to withdraw from the project and claim refund. The Authority emphasized that homebuyers cannot be left in a state of uncertainty where the promoter fails to honour possession commitments.
2. Builder must prove buyer’s default
The Authority held that allegations of default cannot operate as a blanket defence against refund claims. Where a promoter seeks to deny refund or invoke forfeiture, the burden remains on the promoter to establish such default with cogent material and evidence.
3. Refund right is protected under RERA
The order reiterates that RERA is designed not only to regulate developers but also to provide effective remedies to allottees. Refund in delayed possession situations remains one of the strongest statutory protections available to buyers.
4. Supreme Court precedent applied
HRERA relied on Newtech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh, where the Supreme Court recognised the independent statutory right of allottees to seek refund in cases of delayed possession and explained the remedial nature of Section 18 of RERA.
Direction Issued
HRERA directed Manglam Multiplex Private Limited to refund the amount paid by the buyers, subject to permissible deductions, together with interest until actual refund.
Why This Order Matters
The order reinforces a consistent judicial and regulatory trend that places accountability on promoters where project timelines are breached.
For years, delayed possession disputes have formed one of the largest categories of real-estate litigation in India, with buyers often continuing to service financial commitments while receiving no corresponding delivery of housing. Orders such as this reiterate that RERA was intended to correct that imbalance.
This decision also clarifies an important procedural aspect-refund claims cannot be defeated merely by raising general allegations of non-payment or default. If a promoter seeks to retain amounts or resist cancellation, the Authority expects proof and a legally sustainable basis.
For homebuyers, the ruling strengthens confidence that cancellation and refund remain practical statutory options rather than theoretical rights. For promoters, the message is equally clear: possession obligations carry legal consequences and cannot be diluted through unsupported objections.
Latest Legal Position
The legal position emerging from recent developments continues to favour meaningful enforcement of refund remedies under RERA while maintaining respect for statutory finality.
Courts have increasingly emphasised that once RERA proceedings attain finality, such orders cannot be lightly reopened through collateral challenges or writ proceedings merely because parties later seek to rely upon subsequent judicial developments. At the same time, judicial scrutiny continues to preserve the remedial character of RERA and ensure that homebuyers are not deprived of effective relief where delays persist.
This approach reflects a broader judicial balance-protecting promoters from endless litigation while ensuring that allottees retain access to remedies where possession commitments remain unfulfilled.
The continued reliance on Newtech Promoters across forums also indicates that the Supreme Court’s interpretation of allottee rights under RERA continues to guide adjudication across real estate disputes.
Case Details
Case Title: Shashi Saha and Another v. Manglam Multiplex Private Limited
Case No.: CC 1106 of 2022
Forum: Haryana Real Estate Regulatory Authority, Gurugram Bench
Issue: Delayed possession and allottee’s right to refund
Bars Across Note
This order strengthens the position of homebuyers in delayed possession cases and reinforces that statutory protections under RERA cannot be diluted by unsupported allegations.
The decision makes clear that builders cannot defeat refund claims merely by alleging default unless such default is clearly established. Once the promised possession timeline is breached, the allottee’s right to exit the project and seek refund becomes a meaningful statutory remedy.
For practitioners, the ruling highlights the growing importance of placing evidence at the centre of refund disputes and ensuring that allegations of default are tested against actual payment conduct and contractual obligations. For homebuyers, it serves as another reminder that RERA continues to operate as an important corrective mechanism in India’s real-estate ecosystem.
